JP1 Posted September 26, 2004 Share Posted September 26, 2004 Anybody know how long to leave a newly laid concrete floor before its ok to tile.thanks.regardsJP Link to comment Share on other sites More sharing options...
Idealfrance Posted September 26, 2004 Share Posted September 26, 2004 It depends on the thickness of the concrete. We normally use a base of 1 day setting time per cm of thickness. It also depends on the temperature / weather conditions. If your concrete floor is outside then give it longer. Ben Symonshttp://www.idealfrance.com Link to comment Share on other sites More sharing options...
Jackie Posted September 26, 2004 Share Posted September 26, 2004 We were told at least 6 weeks but in fact it was more like two months in the middle of last summer when it was very hot. We have had no problems so far with the tiles I laid then......................John in 79 Link to comment Share on other sites More sharing options...
JP1 Posted September 26, 2004 Author Share Posted September 26, 2004 Thanks for the responses, its for an inside floor and its 3cm thick.regards.JP Link to comment Share on other sites More sharing options...
Recommended Posts
Archived
This topic is now archived and is closed to further replies.